“It was found that a building of 30,000 square meters, 3 hectares, was almost finished, in bulk closed work, while the permit had been refused by the minister,” Raphaël Stokis, an official from the Walloon Department of Spatial Planning and Urbanism told Belgian public broadcaster RTBF.

The suspension follows urgent legal action brought by environmental campaign group Greenpeace over Google’s decision to continue construction despite the annulment of an amended permit.

Google originally obtained permission in 2024 to build three data centers in Belgium using an air-based cooling system. After the request was granted, however, the company applied to modify the permit, reducing the number of data centers from three to two and switching to a water-based cooling system drawing from the nearby River Sambre.

The amended permit was granted in April 2026 but annulled in August following a third-party appeal. Google continued work at the site while challenging that decision, with its appeal before Belgium’s Council of State scheduled to be heard on Jan. 7.

Google maintains that it holds several other permits for the development of the data center campus that remain valid. The company said work undertaken since August was primarily intended to preserve and secure the site during the appeal process, as well as to carry out construction authorized under its original permit.

The dispute comes amid growing opposition to the construction of data centers powering the global AI boom, with their vast energy and water requirements increasingly becoming a political flashpoint for local communities and governments.

Share.
Exit mobile version