Google halts Belgian data center construction amid permit dispute – POLITICO

November 29, 2026

Expect more frequent cyberattacks, warns minister after UK government hack – POLITICO

November 29, 2026

Beach Boys co-founder and lead singer on ‘Surfin USA’, Mike Love dies at 85

November 29, 2026

Europas Milliardenproblem bei der Verteidigung – mit Moritz Schularick – POLITICO

November 29, 2026

Floods hit Peru and Ecuador as powerful El Niño brings torrential rain

November 28, 2026
Facebook X (Twitter) Instagram
Web Stories
Facebook X (Twitter) Instagram
Daily Guardian Europe
Newsletter
  • Home
  • Europe
  • World
  • Politics
  • Business
  • Lifestyle
  • Sports
  • Travel
  • Environment
  • Culture
  • Press Release
  • Trending
Daily Guardian EuropeDaily Guardian Europe
Home»Politics
Politics

Google halts Belgian data center construction amid permit dispute – POLITICO

By staffNovember 29, 20262 Mins Read
Google halts Belgian data center construction amid permit dispute – POLITICO
Share
Facebook Twitter LinkedIn Pinterest Email

“It was found that a building of 30,000 square meters, 3 hectares, was almost finished, in bulk closed work, while the permit had been refused by the minister,” Raphaël Stokis, an official from the Walloon Department of Spatial Planning and Urbanism told Belgian public broadcaster RTBF.

The suspension follows urgent legal action brought by environmental campaign group Greenpeace over Google’s decision to continue construction despite the annulment of an amended permit.

Google originally obtained permission in 2024 to build three data centers in Belgium using an air-based cooling system. After the request was granted, however, the company applied to modify the permit, reducing the number of data centers from three to two and switching to a water-based cooling system drawing from the nearby River Sambre.

The amended permit was granted in April 2026 but annulled in August following a third-party appeal. Google continued work at the site while challenging that decision, with its appeal before Belgium’s Council of State scheduled to be heard on Jan. 7.

Google maintains that it holds several other permits for the development of the data center campus that remain valid. The company said work undertaken since August was primarily intended to preserve and secure the site during the appeal process, as well as to carry out construction authorized under its original permit.

The dispute comes amid growing opposition to the construction of data centers powering the global AI boom, with their vast energy and water requirements increasingly becoming a political flashpoint for local communities and governments.

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

Keep Reading

Expect more frequent cyberattacks, warns minister after UK government hack – POLITICO

Europas Milliardenproblem bei der Verteidigung – mit Moritz Schularick – POLITICO

Albania’s Independence Day rocked by violent protests over corruption – POLITICO

Spanish PM candidate Feijóo visits Ceuta during election blackout day – POLITICO

Greek junior minister resigns amid public contracts controversy – POLITICO

Spain’s far-right kingmaker – POLITICO

Ein Spaziergang mit Markus Frohnmaier – POLITICO

9 things you need to read ahead of the Spanish election – POLITICO

Kushner’s Putin comments spark outrage in Europe – POLITICO

Editors Picks

Expect more frequent cyberattacks, warns minister after UK government hack – POLITICO

November 29, 2026

Beach Boys co-founder and lead singer on ‘Surfin USA’, Mike Love dies at 85

November 29, 2026

Europas Milliardenproblem bei der Verteidigung – mit Moritz Schularick – POLITICO

November 29, 2026

Floods hit Peru and Ecuador as powerful El Niño brings torrential rain

November 28, 2026

Subscribe to News

Get the latest Europe and world news and updates directly to your inbox.

Latest News

Albania’s Independence Day rocked by violent protests over corruption – POLITICO

November 28, 2026

Spanish PM candidate Feijóo visits Ceuta during election blackout day – POLITICO

November 28, 2026

US military fires at a ship that violated blockade of Iranian ports

November 28, 2026
Facebook X (Twitter) Pinterest TikTok Instagram
© 2026 Daily Guardian Europe. All Rights Reserved.
  • Privacy Policy
  • Terms
  • Advertise
  • Contact

Type above and press Enter to search. Press Esc to cancel.